Second Floor Electrical Cable Laying Started on 1st November 2010. One Apartment is completed in 2 days. At this rate 4 days to complete each floor. There are 3 persons laying the cable.
Wednesday, November 3, 2010
Bathroom water proof testing before screed
^ click on image for larger version ^
Waterproofing of first layer of Sika Latex is being tested in all bathrooms in 1st and 2nd floor. The leak is noted in the 2 toilets facing the road side balcony in both 1st and second floor. The wall joint masonry to the slab is to be chipped and repaired with grout mixed with Sika Plastocrete Plus. And will be retested after application of Sika Latex in the repaired joint.
Waterproofing of first layer of Sika Latex is being tested in all bathrooms in 1st and 2nd floor. The leak is noted in the 2 toilets facing the road side balcony in both 1st and second floor. The wall joint masonry to the slab is to be chipped and repaired with grout mixed with Sika Plastocrete Plus. And will be retested after application of Sika Latex in the repaired joint.
Subscribe to:
Comments (Atom)