Ground Floor Trench and Riser Connection
^ click on image for larger version ^
Image showing the 2 options of paths, the sewer line and fresh water lines can take to join the Ground Floor Trench. The GREEN line shows the previous recommendation by the MNE engineer. The RED line shows the new proposed path that can be taken by the sewer line for the 10 bath rooms of this duct. The engineer will mark the ceiling line after the 1:100 level slope is taken by the sewer line on the left hand side (West side). The is to begin tomorrow morning at site as per the path shown in RED.
Appartment level electric DB locations
^ click on image for larger version ^
A mock-up is made from wood indicating the 1m level for the projection wall for fixing the Apartment Floor Level Electric DB. This is the original proposed location for the floor level DBs as viewed from the kitchen side. This option provides some privacy to the apartment, and will sort of be along the side of the sofa set creating a pocket. And people will be moving around from the opposite side which is open.
A mock-up is made from wood indicating the 1m level for the projection wall for fixing the Apartment Floor Level Electric DB. This is the original proposed location for the floor level DBs as viewed from the kitchen side. This option provides some privacy to the apartment, and will sort of be along the side of the sofa set creating a pocket. And people will be moving around from the opposite side which is open.
^ click on image for larger version ^
The wall projection is moved here to the kitchen side. This is viewed from the living room side. The projected wall will be adjacent to the fridge and the washing machine and will act as a cover for the fridge. The wall will now occupy the space of 6 inch earlier allocated for the general lighting switches of the apartment. The switches can now placed on this projection wall.
The wall projection is moved here to the kitchen side. This is viewed from the living room side. The projected wall will be adjacent to the fridge and the washing machine and will act as a cover for the fridge. The wall will now occupy the space of 6 inch earlier allocated for the general lighting switches of the apartment. The switches can now placed on this projection wall.
^ click on image for larger version ^
Here the DB fixing wall is moved to the side of the concrete wall of the lift pit. The projection will be behind the sofa and an be used to hang a decor piece.
Here the DB fixing wall is moved to the side of the concrete wall of the lift pit. The projection will be behind the sofa and an be used to hang a decor piece.