We need to workout the detail for this cross over. The drain and gas pipe comes below the window sill level to avoid the collision of the window frame that opens to the void in the adjacent room. Earlier the AC contractor suggested to embed the AC service line in the wall screed. The AC is too close to the Bedroom door frame hence the AC power socket will move towards the electric duct as much possible to make room on the right hand side.
Saturday, October 30, 2010
MWSC booster pump reference
This is the booster pump for a similar building, We'll have to check with MWSC on the actual size before casting the fixing base inside the security room. The pump will be accessible from the outside of the room.
Perlin anchor strip fixing
Celing level, water marks have been established in 2nd floor all areas. Perlin anchor strip fixing around the perimeter of rooms started. The image shows ongoing work in Apartment A - Living Area.
Ground Floor Trench Works
Ground floor trench works. Excavated and lean concrete and trench base completed in trench area at the front of the plot. Pipe laying started. Duct wall foundation in progress. Well area excavated to make trench in garage area.